NERC RC/TO/BA, CEM & FE Engineering: practice drill
10 realistic exam questions, graded as you go, with the exact rule or statute citation for every answer. Start free, no sign-up.
Timed mock exam
11 questions in 13 minutes, drawn from every topic. No answers shown until the end, then a full score breakdown, your weakest topics and a review of what you missed.
Prices are in US dollars, plus tax where it applies. Stripe, our payment processor, calculates tax at checkout.
All sales are final. If something is really wrong, such as a duplicate charge or a purchase that does not unlock what you bought, write to support@careerexampro.com and we will put it right.
One-time payment. Nothing renews.
You have an exam ticket for this practice test. Start the timed mock exam to use it.
Exact question counts, passing scores, and allowed reference materials vary by testing window and state/agency. Always confirm current rules with the official testing provider.
Sample questions
An industrial manufacturing plant draws a steady real power load of 480 kW at a lagging power factor of 0.80. To eliminate monthly utility kVA demand penalties, the energy manager plans to install shunt power-factor correction capacitors to raise the plant's lagging power factor to 0.96. How many kVAR of capacitance are required, and what is the new apparent power (kVA)?
100 kVAR of capacitance, reducing apparent power from 600 kVA to 500 kVA.
360 kVAR of capacitance, reducing apparent power from 600 kVA to 480 kVA.
220 kVAR of capacitance, reducing apparent power from 600 kVA to 500 kVA.
140 kVAR of capacitance, reducing apparent power from 576 kVA to 500 kVA.
Show the answer
C. 220 kVAR of capacitance, reducing apparent power from 600 kVA to 500 kVA.
Using the power triangle (S = P / PF and Q = P * tan(arccos(PF))): initially at PF_1 = 0.80, S_1 = 480 / 0.80 = 600 kVA and Q_1 = sqrt(600^2 - 480^2) = 360 kVAR. At the target PF_2 = 0.96, S_2 = 480 / 0.96 = 500 kVA and Q_2 = sqrt(500^2 - 480^2) = 140 kVAR. The required shunt capacitor bank is Q_C = Q_1 - Q_2 = 360 - 140 = 220 kVAR, reducing apparent power from 600 kVA to 500 kVA.
Reference: AEE Certified Energy Manager (CEM) Body of Knowledge — Electrical Systems & Power Factor
A 100 kW centrifugal supply fan operates at 1,800 RPM against a pure friction system curve (zero static pressure bias) for 5,000 hours/year. Installing a Variable Frequency Drive (VFD) slows the fan by 20% to 1,440 RPM. Neglecting minor VFD drive losses, what are the new fan shaft power and annual energy savings according to the Affinity Laws?
New shaft power is 51.2 kW (a 48.8% cut), saving 244,000 kWh/year.
New shaft power is 64.0 kW (a 36.0% cut), saving 180,000 kWh/year.
New shaft power is 80.0 kW (a 20.0% cut), saving 100,000 kWh/year.
New shaft power is 40.9 kW (a 59.1% cut), saving 295,500 kWh/year.
Show the answer
A. New shaft power is 51.2 kW (a 48.8% cut), saving 244,000 kWh/year.
By the centrifugal pump and fan Affinity Laws (for a pure friction curve with no fixed static head), flow varies linearly with speed (N_2/N_1 = 0.80), static pressure varies with speed squared (0.80^2 = 0.64), and shaft power varies with the CUBE of speed: P_2 = P_1 * (N_2/N_1)^3 = 100 * (0.80)^3 = 100 * 0.512 = 51.2 kW. Power drops by 48.8 kW (48.8%), yielding annual savings of 48.8 kW * 5,000 h/yr = 244,000 kWh/year.
Reference: AEE CEM Body of Knowledge — Motors, VFDs & Affinity Laws / ASHRAE Handbook — HVAC Systems
During a full-load commissioning test, a water-cooled centrifugal chiller delivers 400 tons of cooling while drawing 240 kW of electrical input power. Using 1 ton = 12,000 BTU/h = 3.517 kW, what are the chiller's kW/ton efficiency and Coefficient of Performance (COP)?
1.67 kW/ton and COP = 2.11.
0.60 kW/ton and COP = 2.11.
0.60 kW/ton and COP = 20.0.
0.60 kW/ton and COP = 5.86.
Show the answer
D. 0.60 kW/ton and COP = 5.86.
Chiller input efficiency is kW/ton = 240 kW / 400 tons = 0.60 kW/ton. Converting cooling capacity to thermal kilowatts gives Q_cool = 400 tons * 3.517 kW/ton = 1,406.8 kW. Therefore COP = Q_cool / W_in = 1,406.8 / 240 = 5.86 (equivalently COP = 3.517 / (kW/ton) = 3.517 / 0.60 = 5.86). Note that 20.0 is the EER (12 / 0.60), not the dimensionless COP.
Reference: AEE CEM Body of Knowledge — HVAC & Chiller Efficiency / ASHRAE Standard 90.1