NERC RC/TO/BA, CEM & FE Engineering: practice drill

10 realistic exam questions, graded as you go, with the exact rule or statute citation for every answer. Start free, no sign-up.

Timed mock exam

20 questions in 24 minutes, drawn from every topic. No answers shown until the end, then a full score breakdown, your weakest topics and a review of what you missed.

Practice tests that prepare you for this exam

Practise by topic

About this exam

Agency / Issuer
NERC / PSI
Region
United States

Exact question counts, passing scores, and allowed reference materials vary by testing window and state/agency. Always confirm current rules with the official testing provider.

Sample questions

Under NERC Reliability Standard BAL-001-2 (Real Power Balancing Control Performance), what are the two mandatory compliance criteria governing a Balancing Authority's long-term CPS1 performance and real-time Balancing Authority ACE Limit (BAAL)?

  1. CPS1 must remain >= 90% on a rolling monthly basis, and clock-minute ACE must not exceed BAAL for more than 15 consecutive minutes.
  2. CPS1 must remain >= 100% on a rolling 30-day basis, and clock-minute ACE must return to zero within 10 minutes of any BAAL excursion.
  3. CPS1 >= 100% over a rolling 12-month period, and clock-minute ACE must not exceed BAAL for > 30 consecutive minutes.
  4. CPS1 must remain >= 95% over a rolling 12-month period, and BAAL applies only when Interconnection frequency falls below 59.95 Hz.
Show the answer

C. CPS1 >= 100% over a rolling 12-month period, and clock-minute ACE must not exceed BAAL for > 30 consecutive minutes.

NERC BAL-001-2 Requirement R1 mandates that each Balancing Authority achieve a Control Performance Standard 1 (CPS1) score of at least 100% over every rolling 12-month period. Requirement R2 establishes the dynamic, frequency-dependent Balancing Authority ACE Limit (BAAL_Low and BAAL_High): a BA's clock-minute average ACE may not exceed its BAAL for more than 30 consecutive clock-minutes.

Reference: NERC BAL-001-2 (Real Power Balancing Control Performance), Requirements R1 & R2

A steam turbine generator rated at 450 MW is operating online at 360 MW with a 5% governor droop setting on a 60.00 Hz Interconnection (assume negligible governor deadband). Following a major transmission and generation disturbance, steady-state Interconnection frequency settles at 59.80 Hz. Assuming the unit is not blocked from governor response, what is its new real power output?

  1. 390 MW, reflecting a +30 MW primary governor response.
  2. 384 MW, reflecting a +24 MW response scaled to its 360 MW dispatch.
  3. 330 MW, reflecting a -30 MW automatic unloading to protect turbine blades.
  4. 450 MW, because any frequency deviation below 59.95 Hz drives the governor valve fully open to maximum rated output.
Show the answer

A. 390 MW, reflecting a +30 MW primary governor response.

A 5% droop on a 60 Hz system corresponds to a 0.05 x 60 = 3.0 Hz frequency change for a 100% swing of rated capacity (450 MW), not current output. Using delta_P = -(delta_F / (F_nom * R)) * P_rated = -((-0.20) / 3.0) * 450 = +30 MW. Since the unit has 450 - 360 = 90 MW of available headroom, its output increases from 360 MW to 390 MW.

Reference: NERC Balancing and Frequency Control Reference Document / IEEE Std 122 (Governor Droop)

During a regional heatwave, a Balancing Authority executes 140 MW of emergency firm load shedding to maintain Bulk Electric System continuity. How do NERC EOP-004-4 and DOE Form OE-417 reporting deadlines interact for this event?

  1. DOE OE-417 requires a 1-hour Emergency Alert for >= 100 MW firm load shedding, which also satisfies EOP-004-4's 24-hour deadline.
  2. NERC EOP-004-4 prohibits using DOE Form OE-417 for load-shedding events and mandates filing two separate written reports within 72 hours.
  3. No federal or NERC event report is required unless involuntary firm load shedding exceeds 500 MW for more than two continuous hours.
  4. DOE Form OE-417 allows up to 24 hours for firm load shedding of any magnitude, whereas NERC EOP-004-4 enforces a strict 15-minute reporting window.
Show the answer

A. DOE OE-417 requires a 1-hour Emergency Alert for >= 100 MW firm load shedding, which also satisfies EOP-004-4's 24-hour deadline.

Under NERC EOP-004-4 Requirement R2, Responsible Entities must report Attachment 1 events by the later of 24 hours of recognition or the end of the next business day (4:00 PM local), and may fulfill this requirement by submitting either Attachment 2 or DOE Form OE-417. Because emergency firm load shedding of >= 100 MW triggers DOE Form OE-417's stricter 1-hour Emergency Alert window, filing OE-417 within 1 hour satisfies both DOE and NERC EOP-004-4.

Reference: NERC EOP-004-4 (Event Reporting), Requirement R2 & Attachment 1 / DOE Form OE-417